Weekly Construction Update: July 10, 2026

By Mary Ellen Murphy Jul 13, 2026 | 8:59 AM

Ottawa County, MI (WGHN) – Here is your weekly construction update from the Ottawa County Road Commission:

 

Road Resurfacing: 120th Ave., M-45 to Taylor St., Olive/Robinson Twps., begins July 13

WHEN: Beginning July 13, 2026

WHERE:120th Ave., M-45 to Taylor St., Olive/Robinson Twps.

WHY: Road Resurfacing

BACKGROUND: Tentatively beginning the week of July 13, 2026, contractors for the Ottawa County Road Commission are expected to begin work on a resurfacing project on 120th Ave. between M-45 and Taylor St. in Olive/Robinson Twps.

Work on this project is expected to last through the end of July, however, please note that all work is weather-dependent, and completion dates are subject to change.

TRAFFIC IMPACT: Traffic will be maintained using temporary lane closures under flag control during work hours. Be prepared for possible delays when traveling through this area while work is taking place.

Road Resurfacing: 160th Ave., South Shore Dr. to Ottogan St., Park Twp., begins July 13

WHEN: Beginning July 13, 2026

WHERE: 160th Ave., South Shore Dr. to Ottogan St., Park Twp.

WHY: Road Resurfacing

BACKGROUND: Beginning June 13, 2026, contractors for the Ottawa County Road Commission are expected to begin work on a resurfacing project on 160th Avenue between South Shore Drive and Ottogan Street in Park Township.

Work on this project is expected to last through late July, however, please note that all work is weather-dependent, and completion dates are subject to change.

TRAFFIC IMPACT: Traffic will be maintained using temporary lane closures under flag control during work hours. Be prepared for possible delays when traveling through this area while work is taking place.

Road Resurfacing: Linden Dr., M-45 to Leonard St., begins July 16

WHAT: Road Resurfacing

WHEN: Beginning July 16, 2026

WHERE: Linden Dr., M-45 to Leonard St., Tallmadge Twp.

BACKGROUND: On Thursday, July 16, 2026, contractors for the Ottawa County Road Commission will begin working on a resurfacing project on Linden Dr. between M-45 and Leonard St. in Tallmadge Township.

This work is expected to last through late July. Please note that all work is weather dependent and completion times are subject to change.

TRAFFIC IMPACT: The road will remain closed to through traffic. A detour route will consist of M-45 to 24th Avenue to Leonard Street.

Current Projects & Closures

TOWNSHIP

ROAD

SEGMENT

WORK

DATES

AUTHORITY

TRAFFIC

Olive/Robinson 120th Ave. M-45 to Taylor St. Resurfacing July 13-24 OCRC Lane Closures
Park 160th Ave. S. Shore Dr. to W. 32nd Ave. Resurfacing July 13-24 OCRC Lane Closures
Crockery Cleveland St. M-104 to 96th Ave. Resurfacing July 7-31 OCRC Lane Closures
Spring Lake Leonard St. Spring Lake Village to 148th Ave. Resurfacing July 7-31 OCRC Lane Closures
Jamestown 24th Ave. Riley St. to Byron Rd. Culvert Replacement July 6-17 OCRC Road Closed
Holland 104th Ave. James St. to Felch St. Bridge Rehab July 6-Nov.30 OCRC Road Closed
Grand Haven/Robinson Lincoln St. At 144th Ave. Roundabout July 6-Aug. 10 OCRC Road Closed
Tallmadge Linden Dr. M-45 to Leonard St. Culvert Replacement/
Resurfacing
July 6-TBD OCRC Road Closed
Blendon Tyler St. 48th Ave. to 56th Ave. Water Main June 22-July 3 Permit Road Closed
Georgetown 42nd Ave. Baldwin St. to Bauer Rd. Resurfacing June 19-July 10 OCRC Lane Closure
Grand Haven Ferris St. 160th Ave. to 168th Ave. Water Main/Pathway June 8-Aug. 15 Permit Road Closed
Allendale 60th Ave Lincoln St. to Comfort Dr. Water Main June 3-July 31 Permit Road Closed
Allendale Warner St. 68th Ave. to 60th Ave. Water Main June 1-July 31 Permit Road Closed
Olive Port Sheldon St. At 120th Ave. Roundabout June 1-July 24 OCRC Road Closed
Georgetown 12th Ave. Port Sheldon St. to Chicago Dr. Bridge Rehabilitation May 26-August 31 OCRC Road Closed
Holland Howard Ave. Jefferson St. to N. River Ave. Inspection May 11-July 17 Permit Road Closed
Olive Van Buren St. 144th Ave. to 136th Ave. Water Main May 4-July 31 Permit Road Closed
Holland Lakewood Blvd. 120th Ave. to U.S. 31 Sanitary Sewer May 4-Nov. 15 Permit Road Closed
Jamestown Adams St. 40th Ave. to 36th Ave. Bridge Rehabilitation April 22-Nov. 6 OCRC Road Closed
Holland 124th Ave. Ransom St. to New Holland St. Road Reconstruction April 13-July 17 Permit Road Closed
Georgetown 12th Ave. Jackson St. North to End Reconstruct April 2-TBD OCRC Road Closed
Georgetown 48th Ave. Port Sheldon St. to Baldwin St. Water Main March 30-Aug. 30 Permit Road Closed
Allendale Pierce St. 52nd Ave. to 56th Ave. Road Work March 9-July 4 Permit Road Closed
Olive New Holland St. 96th Ave. to 104th Ave. Water Main Nov. 12-Aug. 1 Permit Road Closed
Olive Van Buren St. U.S. 31 to 120th Ave. Water Main Nov. 3-Sept. 1 Permit Road Closed
Port Sheldon Van Buren St. Butternut Dr. to 144th Ave. Water Main Sept. 4-Aug. 1 Permit Road Closed

Subdivison Resurfacing Schedule

TOWNSHIP

DATES

Allendale Beginning July 20 (est.)
Jamestown TBD
Park Beginning July 27 (est.)

Information about Township subdivision resurfacing projects can be found on the Township Subdivision Resurfacing project website.